21 |
Ministry of Energy, Power and Minearal Resources
Bangladesh Power Development Board
|
10724, Date:24.06.2025
Design, Supply, Construction, Erection, Installation, Testing & Commissioning of 7 New 33/11kV GIS Substations, 4 Upgraded 33/11kV GIS Substations, 33kV Bay Extension at 5 Substations with Civil Works & SAS-Based Automation on Turnkey Basis
03/08/2023
|
Power Distribution System Development, Chattogram Zone (2nd Phase)
ICT
|
Dhaka |
28/05/2025 |
JV of SPTDE and Reverie
Evergreen Plaza (5th & 7th floor) 260/B Tejgaon I/A, Dhaka-1208, Bangladesh
|
EURO 35,486,420.30 and BDT 823,565,094.44 |
22 |
Ministry of Energy, Power and Minearal Resources
Bangladesh Power Development Board
|
10725, Date:24.06.2025
Design, Supply, Construction, Erection, Installation, Testing & Commissioning of 5 New 33/11kV GIS Substations, 2 Upgraded 33/11kV GIS Substations, 33kV Bay Extension at 2 Substations with Civil Works & SAS-Based Automation on Turnkey Basis
03/08/2023
|
Power Distribution System Development, Chattogram Zone (2nd Phase)
ICT
|
Dhaka |
28/05/2025 |
JV of Reverie-Norinco Intl-DK
Evergreen Plaza (5th & 7th floor), 260/B Tejgaon I/A, Dhaka-1208, Bangladesh
|
USD 13,576,944.87, EURO 22,816,476.01, BDT 689,438,148.60 |
23 |
Ministry of Finance
Economic Relations Devision
|
09.00.0000.228.07.129.23.230
Comprehensive Stady on TVET skills maping
18/12/2024
|
Project Director, SSGP
NCT
|
Dhaka |
27/05/2025 |
IIFC
Tejgaon Dhaka-1215
|
7100000 |
24 |
Ministry of Post, Telecommunications & Information Technology
Bangladesh computer Council (BCC)
|
56.01.0000.046.07.049.2023-1408
Supply, Installation and Commissioning for Expansion of the Cloud Platform(IaaS) in the National Data Center at BCC, Lot-1: Expansion of Nutanix Private Cloud Platform at the National Data Center, BCC
14/12/2023
|
Project Director, Enhancing Digital Government and Economy (EDGE) Project
ICT
|
Dhaka |
25/05/2025 |
Thakral Information Systems Private Limited
11th Floor (East), BDBL (Former-BSRS) Bhaban, 12 Kawran Bazar, Dhaka-1215, Bangladesh
|
US$ 4,698,287.11 (USD Four Million Six Hundred Ninety Eight Thousand Two Eighty Seven Hundred point Eleven Only) |
25 |
Ministry of Post, Telecommunications & Information Technology
Bangladesh Telecommunications Company Ltd. (BTCL)
|
14.33.0000.315.07.019.24.55; Date: 09-01-2025
Supply, Installation, Testing and Commissioning of Optical Fiber Cable Network
13/01/2025
|
Project Director, Development of Optical Fiber Transmission Network of BTCL for 5G Readiness Project
NCT
|
Dhaka |
12/05/2025 |
M/s Hamida Traders Limited
Mahtab Center (11th floor), 177 Shaheed Syed Nazrul Islam Sarani, Bijoy Nagar, Dhaka-1000
|
364566344.00 |
26 |
Ministry of Post, Telecommunications & Information Technology
Bangladesh Telecommunications Company Ltd. (BTCL)
|
14.33.0000.315.07.019.24.55; Date: 09-01-2025
Supply, Installation, Testing and Commissioning of Optical Fiber Cable Network
13/01/2025
|
Project Director, Development of Optical Fiber Transmission Network of BTCL for 5G Readiness Project
NCT
|
Dhaka |
12/05/2025 |
M/s Hamida Traders Limited
Mahtab Center (11th floor), 177 Shaheed Syed Nazrul Islam Sarani, Bijoy Nagar, Dhaka-1000
|
307033752.00 |
27 |
Ministry of Water Resources
Bangladesh Water Development Board (BWDB)
|
42.01.0000.039.14.004.23-399, Date:25-06-2024.
Detailed Feasibility Study for Integrated Development of Selected Stable Chars in the Meghna Estuary for Implementation under CDSP V and Erosion Management Plan at Boyer Char, Char Nangulia and Noler Char under Char Development and Settlement Project- Bridging (Additional Financing) (BWDB Part)
20/12/2023
|
Project Director, Char Development and Settlement Project-Bridging (Additional Financing) (BWDB Part)
NCT
|
Dhaka |
05/05/2025 |
Institute of Water Modelling (IWM) in association with Sub-consultant Knowledge Management Consultants (KMC) Ltd, Bangladesh, House # 6, Road # 3C, Block # H, Sector # 15, Uttara, Dhaka-1230
Noakhali, Lakshmipur, and Bhola Districts
|
BDT 9,21,67133.34/- (Taka Nine Crore Twenty-One Lakh Sixty-Seven Thousand One Hundred Thirty-Three Point Three Four Only). |
28 |
Ministry of Finance
Jiban Bima Corporation
|
53.19.0000.401.40.001.24-61
Design & Development , Implementaion and Maintenance of Bancassarance System with Customization of JBC'se Insurance system ( Core insureance ) for Bancassurance and integration with Banks. Core Insurance and Others.
24/11/2024
|
General Manager ,ICT Division
ICT
|
Dhaka |
04/05/2025 |
Synesis IT Ltd.
Dhaka
|
2,46,66,127.50 |
29 |
Ministry of Fisheries & Livestock
Department of Fisheries
|
Contract No. 2024-25/SD64/81 Date: 24/04/2025
Third-Party Assessor for Endline Assessment and Project Completion Report
22/11/2024
|
Project Director, Sustainable Coastal and Marine Fisheries Project, Department of Fisheries
NCT
|
Dhaka |
24/04/2025 |
Joint Venture of HV-PMID
[Joint Venture of HV Associates Limited (HV) (Lead Firm) and Participatory Management Initiative for Development (PMID) (Member Firm)]
House No 7/Ka, Flat No 1-C (1st Floor)
Garden Street, Ring Road
Shyamoli, Dhaka-1207, Bangladesh
|
23122027.78 |
30 |
Ministry of Post, Telecommunications & Information Technology
Information and Communication Technology Division
|
56.83.0000.000.006.07.0008.25.486/2
Framework Agreement of Food and Refreshment Items for a2i Programme
23/02/2025
|
Project Director, Aspire to Innovate (a2i) Programme
NCT
|
Dhaka |
24/04/2025 |
White Castle Restaurant
3/a,Block-A,Lalmatia
|
16,72,000.00 |