Ministry/Division : |
: |
Ministry of Road Transport and Bridges |
Agency : |
: |
Roads & Highways Department (RHD) |
Procuring Entity Name : |
: |
Project Director (ACE, RHD) SASEC Road Connectivity Project-II: Improvement of Elenga-Hatikamrul -Rangpur Road to a 4-Lane Highway |
Procuring Entity Code : |
: |
|
Procuring Entity District : |
: |
Dhaka |
Invitation For |
: |
Works |
Invitation Reference No |
: |
35.RHD.0000.PDSASEC-II.07.004.2017-78 |
Date |
: |
30/01/2018 |
KEY INFORMATION
|
Procurement Method |
: |
ICT Open Tendering Method |
FUNDING INFORMATION
|
Budget and Source of Funds : |
: |
Development Budget Grant/Credit |
Development Partner |
: |
Asian Development Bank (ADB)
|
PARTICULAR INFORMATION
|
Project/Programme Code |
: |
|
Project/Programme Name |
: |
|
Tender Package No |
: |
SASEC-II/ICB/MP-3/WP 10 (LOT 1); SASEC-II/ICB/MP-3/WP 11 (LOT 2) and SASEC-II/ICB/MP-3/WP 12 (LOT 3) |
Tender Package Name |
: |
SASEC-II/ICB/MP-3/WP 10 (LOT 1); SASEC-II/ICB/MP-3/WP 11 (LOT 2) and SASEC-II/ICB/MP-3/WP 12 (LOT 3); SASEC Road Connectivity Project-II: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-Lane Highway. |
Tender Publication Date |
: |
18/02/2018 |
Tender Last Selling Date |
: |
19/03/2018 |
Tender Closing Date and Time |
: |
20/03/2018 12:00 PM |
Tender Opening Date and Time |
: |
20/03/2018 12:30 PM |
Office Address Information |
Selling Tender Document (Principal)
|
"Project Director (ACE, RHD)
SASEC Road Connectivity Project-II:
Improvement of Elenga - Hatikumrul - Rangpur Road to a 4-Lane Highway
Address: Room No. 203, Block H, Sarak Bhaban, Tejgaon, Dhaka-1208, Bangladesh." |
Receiving Tender Document
|
"Project Director (ACE, RHD)
SASEC Road Connectivity Project-II:
Improvement of Elenga - Hatikumrul - Rangpur Road to a 4-Lane Highway
Address: Room No. 203, Block H, Sarak Bhaban, Tejgaon, Dhaka-1208, Bangladesh." |
Opening Tender Document
|
"Project Director (ACE, RHD)
SASEC Road Connectivity Project-II:
Improvement of Elenga - Hatikumrul - Rangpur Road to a 4-Lane Highway
Address: Room No. 203, Block H, Sarak Bhaban, Tejgaon, Dhaka-1208, Bangladesh." |
Selling Tender Document (Others)
|
- |
|
Place/Date/Time of Tender Meeting (Optional) |
: |
Place : Chief Engineer’s Conference Room, Sarak Bhaban, Tejgaon, Dhaka. Bangladesh
Date: 26/02/2018 Time: 12:30 PM |
INFORMATION FOR TENDERER
|
Eligibility of Tenderer : |
: |
4. Only eligible Bidders with the following key qualifications should participate in this Bidding:
(i) The Bidder shall have a Minimum Average Annual Construction Turnover of US$ 71.00 million for SASEC-II/ICB/MP-3/WP 10 (LOT 1); US$ 49.00 million for SASEC-II/ICB/MP-3/WP 11 (LOT 2) and US$ 44.00 million for SASEC-II/ICB/MP-3/WP 12 (LOT 3); calculated as total certified payments received within the last 5 (five) years for contracts in progress or completed.
(ii) Bidder participated in at least One Contract that has been successfully or substantially completed within the last 10 (Ten) years and that is similar to the proposed highway standard road and structure works, where the value of the Bidder’s Participation exceeds US$ 84 million for SASEC-II/ICB/MP-3/WP 10 (LOT 1); US$ 58 million for SASEC-II/ICB/MP-3/WP 11 (LOT 2) and US$ 52 million for SASEC-II/ICB/MP-3/WP 12 (LOT 3). The similarity of the Bidder’s Participation shall be based on the physical size, nature of works, complexity, methods, technology or other characteristics as described in Section 6, Employer’s Requirements. The complete eligibility and qualification requirements are stipulated in Section 3: Evaluation and Qualification Criteria of Bidding Documents. |
Brief Description of Goods or Works : |
: |
ICB No.: SASEC-II /ICB/MP-3/WP 10 (LOT 1) Part 1: Improvement of Road from Mokamtala to Polashbari (29.9km) to a 4-Lane Highway along with Slow Moving Vehicular Traffic (SMVT) Lanes on both sides & Structures. Completion Time for Construction phase works is1095 days.
And Part-2: Performance Based Maintenance Works on Improved 4-Lane Highway from Mokamtala to Polashbari (29.9km) to a 4-Lane Highway along with Slow Moving Vehicular Traffic (SMVT) Lanes on both sides & Structures. Completion Time for Maintenance Phase works is 2190 days.
ICB No.: SASEC-II /ICB/MP-3/WP 11 (LOT 2) Part 1: Improvement of Road from Polashbari to Borodargah Bus Stand (27.2km) to a 4-Lane Highway along with Slow Moving Vehicular Traffic (SMVT) Lanes on both sides & Structures. Completion Time for Construction phase works is1095 days.
And Part 2: Performance Based Maintenance Works on Improved 4-Lane Highway from Polashbari to Borodargah Bus Stand (27.2km) to a 4-Lanes Highway along with Slow Moving Vehicular Traffic (SMVT) Lane on both sides & Structures.Completion Time for Maintenance Phase works is 2190 days.
ICB No.: SASEC-II /ICB/MP-3/WP 12 (LOT 3) Part 1: Improvement of Road from Borodargah Bus Stand to Rangpur (23.8km) to a 4-Lane Highway along with Slow Moving Vehicular Traffic (SMVT) Lanes on both sides & Structures. Completion Time for Construction phase works is 1095 days.
And
Part 2: Performance Based Maintenance Works on Improved 4-Lane Highway from Borodargah Bus Stand to Rangpur (23.8km) to a 4-Lane Highway along with Slow Moving Vehicular Traffic (SMVT) Lanes on both sides & Structures. Completion Time for Maintenance Phase works is 2190 days. |
Brief Description of Related Services : |
: |
Interested eligible Bidders may obtain further information and inspect the Bidding Documents during normal office hours (from 9:00 am to 5:00 pm) on all working days (Sunday to Thursday) up to 19 March 2018 (Monday) at the given address. 6. A complete set of Bidding Documents for each lot may be purchased by interested eligible Bidders upon payment of non-refundable fees of Tk. 15,000 or US$ 180 and upon submission of a written application to the address above during normal office hours on all working days up to the day before the submission deadline (i.e. up to 19 March 2018). The Bidding Documents may also be sent via courier with an additional fee of Tk.60,000 or $750 for each Lot for overseas delivery only. No liability will be accepted for loss or late delivery of the Bidding Documents. The method of payment will be either in Cash or Pay Order / Demand Draft from any scheduled bank in Bangladesh in favor of Project Manager-6, SASEC Road Connectivity Project-II. 7. A Pre-Bid meeting will be held at the Conference Room of the Office of the Chief Engineer, Sarak Bhaban, Tejgaon, Dhaka. Bangladesh on 26 February 2018 (Monday) at 10:30 hrs. (Bangladesh Standard Time). 8. Bids must be delivered to the address above on or before the Bid submission deadline i.e. 20 March 2018 (Tuesday) at 12:00 hrs. (Bangladesh Standard Time). All Bids must be accompanied by a Bid Security in the amount as stated in the Bidding Documents (Data Sheet). Bids submitted after the deadline shall be rejected. The Technical Proposal of the Bids will be opened at the address above at 12:30 hrs. (Bangladesh Standard Time) on 20 March 2018 in the presence of the Bidders’ Representatives who choose to attend. The price proposal of responsive Bids will be opened in presence of the Bidder’s authorized representative who choose to attend at the time, date and address to be advised by the Employer after approval of Evaluation Report of the Technical Proposal by the competent authority with no objection from ADB.
9. RHD will not be responsible for any costs or expenses incurred by Bidders in connection with the preparation or delivery of Bids.
10. The Employer reserves all the rights to accept any Bid or to reject any or all Bids without assigning any reasons whatsoever.
11. The Invitation for Bids (IFB) is available in Roads and Highways Department (RHD), Road Transport and Highways Division, Central Procurement Technical Unit (CPTU) and Asian Development Bank (ADB) websites at www.rhd.gov.bd, www.rthd.gov.bd, www.cptu.gov.bd and www.adb.org respectively, as well as in DG Market (www.dgmarket.com). |
Tender Document Price : |
: |
15000 |
Tender Lot Information |
Lot No |
Identification |
Location |
Security Amount |
Completion Time in Weeks/Months |
1 |
ICB No.: SASEC-II /ICB/MP-3/WP 10 (LOT 1) |
Mokamtala to Polashbari |
102000000 |
120 Months |
2 |
ICB No.: SASEC-II /ICB/MP-3/WP 11 (LOT 2) |
Polashbari to Borodargah Bus Stand |
70000000 |
120 Months |
3 |
ICB No.: SASEC-II /ICB/MP-3/WP 12 (LOT 3) |
Borodargah Bus Stand to Rangpur |
63000000 |
120 Months |
|
PROCURING ENTITY DETAILS
|
Name of Official Inviting Tender : |
: |
Quazi Shahriar Hossain |
Designation of Official Inviting Tender : |
: |
Project Director (ACE, RHD) SASEC Road Connectivity Project-II: Improvement of Elenga - Hatikumrul - Rangpur Road to a 4-Lane Highway |
Address of Official Inviting Tender : |
: |
Room No. 203, Block H, Sarak Bhaban, Tejgaon, Dhaka-1208, Bangladesh. |
Contact Details of Official Inviting Tender : |
: |
Phone: 8802 - 8870100 , Fax: 8802- 8870199, Email: pd.sasecii.rhd@gmail.com |
The procuring entity reserves the right to accept or reject all tenders |